ANALISIS KEBUTUHAN TENAGA KERJA DAN PERALATAN PADA PROYEK PENINGKATAN JALAN: Studi Pada Pelaksanaan Proyek Peningkatan Jalan Pancor - Rempung

INDRA ARISANDI, I GEDE PUTU WARKA, ZAEDAR GAZALBA

Abstract


The Pancor-Rempung road improvement project is delayed. Implementation planning, so that it is needed to optimize the use of labor and equipment so that time and costs can be controlled properly.

The analysis is carried out by calculating the production capacity of each heavy equipment, in order to obtain the value of productivity and labor coefficient. Productivity values and labor coefficients are used to calculate labor and peratan needs based on implementation time schedules and based on optimization of equipment production capacity.

From the results of the calculation of labor requirements and equipment based on time schedule, the need for 1 unit excavator (196 hours), 7 units of dump trucks (588 hours), 3 units of motor grader (343 hours), 2 unit wheel loaders (588 hours), vibrator roller 3 units (343 hours), water tank truck 2 units (441 hours), aspalt mixing palnt 1 unit (245 hours), asphalt finisher 1 unit (245 hours), tandem roller 1 unit (245 hours), pneumatic tire roller 1 unit (245 hours), 1 unit air compressor (245 hours), 1 unit asphalt sprayer (245 hours), 1 unit concrete pan mixer (98 hours, concrete truck mixer 3 units (98 hours), 4 workers (686 hours ), and foreman 4 people (686 hours), with a total cost of IDR 4,074,053,795.00 while the need for labor and equipment based on optimization of equipment production capacity, obtained the need for 1 unit excavator (28 hours, 24 truck dump trucks (105 hours ), motor grader 1 unit (98 hours), wheel loader 1 unit (105 hours), roller vibrator 1 unit (98 hours), water tank truck 1 unit (98 hours ), aspalt mixing palnt 1 unit (35 hours), asphalt finisher 1 unit (35 hours), tandem roller 1 unit (35 hours), pneumatic tire roller 1 unit (35 hours), air compressor 1 unit (35 hours), asphalt sprayer 1 unit (35 hours), concrete pan mixer 1 unit, (28 hours), concrete truck mixer 9 units (28 hours), workers 9 people (161 hours) and foreman 2 people (161 hours), with a total cost of Rp. 1,382,258,857.00. In calculating labor requirements and equipment based on the time schedule obtained several jobs have a small time factor of labor and equipment, due to the long duration of work time and good equipment production capacity.


Keywords


needs, productivity, labor coefficient, and time schedule

Full Text:

PDF

References


Anonim,1997. Manajemen Konstruksi, Ditjen Dikti Depdikbud, Cisarua – Bogor

Anonim,2010. Peraturan Presiden RI No 54 Tahun 2010 Tentang Pengadaan Barang dan Jasa Pemerintah, Jakarta

Anonim.2014. Spesipikasi Teknik PT.Bahagia Bangun Nusa, Mataram

Anonim.2012. Analisa Satuan Pekerjaan (AHSP) Bidang Pekerjaan Umum.Kementerian Pekerjaan Umum RI, Jakarta

Fadhil, M.2011.Perencanaan Alokasi Material dan Tenaga Kerja pada Proyek Pembangunan Gedung & Lab. Balai POM Makasar.” Jurnal Tugas Akhir Universitas Hasanudin Makasar.

Fatmasari,Bq.A.2012. Analisis Biaya Operasi Alat Pemecah Batu (Studi Kasus PT. Kresna Karya Pringgabaya Lombok TImur)”.Tugas Akhir Jurusan Teknik Sipil Universitas Mataram

Hapsari,Ilham.2013. Perencanaan Tenaga Kerja dan Biaya Pekerjaan Beton Struktur pada Proyek Pembangunan Gedung Samsat Praya Lombok Tengah. Tugas Akhir Jurusan Teknik Sipil Universitas Mataram.

Husein,Abrar.2009.ManajemenProyek(Perencanaan,Penjadwalan,&PengendalianProyek).

C.V Andi Offset Yogyakarta.

Hendra, S. & Haryanto, Y.W.. 1998.Alat – Alat Berat. Universitas Atma Jaya Yogyakarta.

Murtif,Nazly. 2013. Alokasi Kebutuhan Alat Berat pada Proyek Pelebaran Jalan A.P Pettarani Makasar. Jurnal Tugas Akhir Universitas Hasanudin Makasar.

Rochmanhadi.1992. Alat-alat Berat dan Penggunaannya. Yayasan Badan Penerbit Pekrjaan Umum. Jakarta

Rostiyanti,Susi Fatena.2002. Alat – Alat Berat untuk Proyek Konstruksi.Jakarta:PT. Ashadi Mahasatya Jakarta.




DOI: https://doi.org/10.35327/gara.v12i2.33

Refbacks

  • There are currently no refbacks.


Copyright (c) 2018 GANEC SWARA

Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

TERINDEKS

 

 

 

 

 

 

 


_______________________________

Ganec Swara

Published by UNMAS Denpasar K. Mataram |
Email: ganecswara@gmail com; aminullahmtk@gmail.com

Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

    
Stat Pengunjung GARA