Projects for the extension of the runway and other supporting facilities at the international airport of Lombok, Central Lombok, West Nusa Tenggara (NTB), where the implementation of the work is dominated by the use of heavy equipment to accelerate the completion of the work.

The data obtained is by direct observation in the field. Analysis of the calculation of heavy equipment productivity, heavy equipment operating costs, revenue and profit were analyzed using the Bina Marga method. The heavy equipment studied in the field are excavators, dump trucks, motor graders, vibrator rollers, and water tankers.

Productivity and the number of tools needed from the analysis results with those in the contract documents are appropriate, while the duration or time of work from the analysis results is more efficient. The hourly rental fee obtained from the calculation results for each heavy equipment, namely Excavator, is Rp. 694,260. Dump trucks of Rp. 753,762. Motor grader Rp. 642.188. Vibratorroller Rp. 551583.4. As for the Watertanker Rp. 384,646.04. The income and profit obtained from the use of heavy equipment on the ground work of the runway extension project at the Lombok international airport with a total of Rp. 38,279,148,142.96 and a profit of Rp. 3,469,922,558.05.


Keywords


Heavy equipment, Productivity, Operational costs

Full Text:

PDF

References


Anonim. (2018). Pedoman Analisis Harga Satuan Pekerjaan Edisi 216. Kementrian PU: Jakarta.

Kholil, Ahmad. (2012). Alat Berat. PT. Remaja Rosda Karya Offset: Bandung.

Mubarok, Ahmad. (2014). Perencanaan Pemakaian Alat Berat Pada Pekerjaan Tanah Proyek Pembangunan Jalan Tol Surabaya – Mojokerto Seksi IV.3 Sta 37+297 s/d Sta 42+800, Institut Teknologi Sepuluh Nopember: Surabaya.

Muis. (2017). Analisis Produktivitas dan Efisiensi Alat Berat Pada Proyek Peningkatan Jalan Kabupaten Paket IV Ruas Pemepek – Repok Pidendang (Lombok Tengah,), Universitas Mataram, Mataram.

Puri, Cahya A. (2020). Analisa Produktivitas Dan Biaya Operasional Alat Berat Pada Proyek Pembangunan Street - Race Circuit Mandalika: Universitas Mataram, Mataram.

Rochmanhadi. (1982). Alat Berat dan Penggunaannya : Deartemen Pekerjaan Umum, Jakarta.

Rostiyanti, Susy Fatena.. (2008). Alat Berat Untuk Proyek Konstruksi, Cetakan I, Edisi 2, Penerbit Rineka Cipta: Jakarta.

Tenrisukki T., Andi. (2003). Pemindahan Tanah Mekanis :Seri Diklat Kuliah. Gunadarma: Jakarta.

Tauro, 2013, Analisis Biaya Penggunaan Alat Berat Pada Pekerjaan Tanah (Studi Kasus Perencanaan Bandar Udara Lokasi Desa Pusugi Kec. Ampena Tete Kab. Tojo Una-Una, Sulawesi Tengah).




DOI: https://doi.org/10.35327/gara.v16i2.328

Refbacks

  • There are currently no refbacks.


Copyright (c) 2022 GANEC SWARA

Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

TERINDEKS

 

 

 

 

 

 

 


_______________________________

Ganec Swara

Published by UNMAS Denpasar K. Mataram |
Email: ganecswara@gmail com; aminullahmtk@gmail.com

Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

    
Stat Pengunjung GARA