Scheduling in the sense of a construction project is a tool to determine the activities needed to complete a project in a certain sequence and time frame, where each activity must be carried out so that the project is completed on time at an economical cost. In this study, the researcher evaluates the reasonableness of the contractor's schedule with the researcher's schedule from the Microsoft Project.

This study was conducted to analyze the reasonableness of the contractor's schedule whether the contractor's schedule is in accordance with the reality on the ground. The data used in this study is secondary data in the form of working drawings and s curves. Analysis of this schedule using the Microsoft project application. Data analysis is carried out by making basic assumptions of building construction, creating a scope of work, making work durations, making relationships between jobs and then analyzing them in the Microsoft project application.

The criteria for the fairness of the schedule are seen from the order of work, work items and work duration. The results showed that of the four contractor schedules at SDN 5 Sokong that met the fair criteria, only the CV UTAMA schedule

Keywords


Discharge, experimental model, scouring pattern, downstream weir

Full Text:

PDF

References


Akhsanitaqwim, Lalu. (2018). Monitoring dan Evaluasi Time Schedule Proyek menggunakan metode Tracking Progres pada Software Microsoft Project.Tugas Akhir. Jurusan Teknik Sipil Fakultas Teknik Universitas Mataram

Anonim. (2011). Kupas Tuntas Microsoft Project 2010. Penerbit C.V Andi Offset. Jogjakarta.

Anonim. (2014). Pedoman Penulisan Tugas Akhir. Jurusan Teknik Sipil. Universitas Mataram.

Atmoko, Eko Hari & Sutanto, Aftoni. 2014. “Microsoft Office Project & MYOB Accounting’. CV Andi Offset. Yogyakarta.

Budi Santosa. (2009). Manajemen Proyek Konsep dan Implementasi. Graha Ilmu. Jakarta.

Callahan M.T. (1992). Construction Project Schedulling. McGraw Hill. Inc.

David M, Walean. (2012). Perencanaan dan Pengendalian Jadwal dengan menggunakan Program Microsoft Project 2010. Tugas Akhir. Jurusan Teknik Sipil Fakultas Teknik Universitas Sam Ratulangi. Manado.

Dimyati, Hamdan & Nurjaman, Kadar. (2014). “Manajemen Proyek”. CV Pustaka Setia. Bandung.

Dunn, William N. (2000). Pengantar Analisis Kebijakan Publik. Gadjah Mada University Press, Yogyakarta.

Fikri, M. Azharul. (2016). Monitoring Proyek Dengan Metode Monte Carlo Pada Durasi Pekerjaan (Studi Kasus Proyek Pembangunan Gedung Bank Muamalat Indonesia Cabang Malang). Tugas Akhir. Jurusan Teknik Sipil Fakultas Teknik Universitas Brawijaya Malang.

Gazalba, Zaedar. (2005). Manajemen Konstruksi. Penerbit Mataram University Press. Mataram.

Husen, Abrar. (2011). Manajemen Proyek. Penerbit C.V Andi Offset. Jogjakarta.

Imam Soeharto. (1999). Manajemen Proyek jilid I dan II. Erlangga. Jakarta.

Marchewka, J. T., (2015). Information Technology ProjectManagement. 5th ed. Hoboken: John Wiley.

Satzinger, J. W., Jackson, R. B. & Burd, S. D., (2012). System Analysis And Design In A Changing World. 6th ed. Boston: Joe Sabatino.

Widiasanti, Irika. (2013). Manajemen Konstruksi. Penerbit PT. Remaja Rosdakarya. Bandung.

Wulfram I, Ervianto. (2000). Manajemen Proyek Konstruksi (Edisi Revisi). ANDI. Yogyakarta.




DOI: https://doi.org/10.35327/gara.v16i1.264

Refbacks

  • There are currently no refbacks.


Copyright (c) 2022 GANEC SWARA

Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

TERINDEKS

 

 

 

 

 

 

 


_______________________________

Ganec Swara

Published by UNMAS Denpasar K. Mataram |
Email: ganecswara@gmail com; aminullahmtk@gmail.com

Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

    
Stat Pengunjung GARA